Chicago Avenue & Division St. Bridge Project updates

By
North Branch Works
September 21, 2026

On September 15th, North Branch Works hosted a meeting with CDOT regarding the latest updates on the Chicago Avenue and Division Street Bridge replacement projects.

Nearly twenty attendees participated in the meeting. The following project timelines were shared:

Chicago Avenue River Bridge & Chicago-Halsted Viaduct Project:

  • Phase I & II, engineering stages were completed in 2025
  • Phase III, construction phase will be completed by the end of 2026
  • Vehicle and truck detours are in place during construction
  • The existing Chicago Avenue temporary bridge will be removed to make way for the new fixed tied-arch bridge and river walk over the North Branch of the river

Division Street Bridges and Division Street Roadway Implementation:

  • Construction is expected to begin at the end of Q1
  • The existing bascule bridge over the River will be removed. This will be replaced with a fixed but potentially movable, tied-arch bridge
  • Remove the existing temporary bridge over the Canal and replace with a fixed thrust-arch bridge
  • There is no detour, instead a Run-a-round (diversion) will be used for both bridges

The presentation slides can be found here:

We are actively receiving updates about the projects, and regularly share infrastructure updates on our blog. You can also see updates on Instagram @northbranchworks.

Please direct any questions to phoebe@northbranchworks.org.

Support local business.

Your donation contributes in meaningful ways towards community building, commerce, and job creation.
Donate today →
Lorem ipsum dolor sit amet, consectetur adipiscing elit. Donec vehicula quis turpis vel sagittis. Nunc vel tortor eu urna hendrerit placerat. Fusce feugiat purus vel velit iaculis pretium.
– John Smith, CEO of a very important business