On September 15th, North Branch Works hosted a meeting with CDOT regarding the latest updates on the Chicago Avenue and Division Street Bridge replacement projects.
Nearly twenty attendees participated in the meeting. The following project timelines were shared:
Chicago Avenue River Bridge & Chicago-Halsted Viaduct Project:
- Phase I & II, engineering stages were completed in 2025
- Phase III, construction phase will be completed by the end of 2026
- Vehicle and truck detours are in place during construction
- The existing Chicago Avenue temporary bridge will be removed to make way for the new fixed tied-arch bridge and river walk over the North Branch of the river
Division Street Bridges and Division Street Roadway Implementation:
- Construction is expected to begin at the end of Q1
- The existing bascule bridge over the River will be removed. This will be replaced with a fixed but potentially movable, tied-arch bridge
- Remove the existing temporary bridge over the Canal and replace with a fixed thrust-arch bridge
- There is no detour, instead a Run-a-round (diversion) will be used for both bridges
The presentation slides can be found here:
We are actively receiving updates about the projects, and regularly share infrastructure updates on our blog. You can also see updates on Instagram @northbranchworks.
Please direct any questions to phoebe@northbranchworks.org.